Performed works: Construction of substation of PS 110/35/6kB «Ventilating well No. 3»
Client: LLC «AEK»
Completed: 2013 – now
PROJECT DETAILS:
year 2013 – now
BUSINESS LINE
Construction of facilities and structures for special purposes
SPECIFICATIONS
The total staff of the main stage of installation: 22 hum.
Duration of work: 5 mon.
The total area of ​​the complex: 700 m 2